Make the passive node active, go to the desktop of that node, and ensure that
cluster resources are offline.
- While you are still on the active data tier node that you just upgraded,
fail over to the
other node make it
active.
- Go to the desktop of the new active node to begin the upgrade process on the second
data tier.
- In Failover Cluster Manager or Cluster Adminstrator on the active
node, make sure the following Sybase Unwired
Platform/SAP Mobile Platform resources are offline:
- Sybase Unwired Server service (named SAP Mobile
Server in
SAP Mobile Platform 2.3)
- Sybase Control Center X.X service (named SAP Control Center X.X service
in SAP Mobile Platform 2.3)
- Unwired SampleDB service (named SAP Mobile Platform SampleDB service in
SAP Mobile Platform 2.3; not present in Enterprise
Server Edition)