Shut down Unwired Platform services on cluster nodes in an exact sequence and take
cluster resources offline on the active node.
- Make sure the active data tier node is on the same host server as
the primary Unwired Server
node.
If it is not, use Failover Cluster Manager to move the cluster's File Server
service to the other data tier node.
- Shut down the secondary Unwired Server – shut down services in this order:
- Sybase Unwired Server
- Sybase Control Center X.X
- Shut down the primary Unwired Server – shut down services in this order:
- Sybase Unwired Server
- Sybase Control Center X.X
- Go to the desktop of the active node.
- In Failover Cluster Manager on the active node, make sure the following Unwired
Platform resources are offline:
- Advantage Database
Server® service
- Afaria Database service
(available with Unwired Platform version 1.5.2 or earlier)
- Sybase Unwired CacheDB service
- Sybase Unwired ClusterDB service
- Sybase Unwired LogDataDB service
- Sybase Unwired SampleDB service
- Proceed with the first host upgrade on the active node.