Preparing for the First Data Tier Upgrade

Shut down Unwired Platform services on cluster nodes in an exact sequence and take cluster resources offline on the active node.

  1. Shut down the Sybase Unwired Server service on each scale-out node.
  2. Shut down the secondary Unwired Server – shut down services in this order:
    1. Sybase Unwired Server
    2. Sybase Control Center X.X
    3. Sybase Unwired SampleDB (not present in Enterprise Server Edition)
  3. Shut down the primary Unwired Server – shut down services in this order:
    1. Sybase Unwired Server
    2. Sybase Control Center X.X
    3. Sybase Unwired SampleDB (not present in Enterprise Server Edition)
  4. In Failover Cluster Manager or Cluster Adminstrator on the active node, make sure the following Unwired Platform resources are offline:
    • Advantage Database Server® service
    • Afaria Database service (available with Unwired Platform version 1.5.2 or earlier)
    • Sybase Unwired CacheDB service
    • Sybase Unwired ClusterDB service
    • Sybase Unwired LogDataDB service
  5. Shut down the data tier server – shut down these services, in any order:
    • Sybase Unwired CacheDB service
    • Sybase Unwired ClusterDB service
    • Sybase Unwired LogDataDB service