Critical Prerequisite Tasks

Perform all critical tasks before you attempt to install the first data tier in your Microsoft Failover Cluster environment.

  1. Set up the number of physical servers that your Unwired Platform installation plan requires.
    Ensure that these hosts meet all the requirements specified in Supported Hardware and Software.
  2. Have your IT support team set up and build a Microsoft Failover cluster with two server nodes on which you will install Unwired Platform data tiers.
    Supply your IT support team with the names for the cluster and the two servers.
  3. Acquire a license file, customized to reflect the Unwired Platform configuration your company has purchased, from SAP Service Marketplace (SMP) or Sybase Product Download Center (SPDC), as described in Obtaining a License.
  4. Install and configure a SySAM license server that can manages license information for all the data tiers and Unwired Server nodes in your cluster.
    For more complete information about SySAM, see:
    Note: You cannot use the unserved license model in a Microsoft Failover Cluster.