Scheduling a Row Comparison Job

Schedule a Data Assurance (DA) row comparison job.

  1. In the Perspective Resources view, select a DA server.
  2. Select Resource > Administration Console.
  3. Expand Data Assurance Server, then select Data Assurance Jobs.
  4. Select a row comparison job, then either:
    • Select Resource > Properties, or,
    • Click the button that appears when you select a row comparison job, then select Properties.
  5. Select Schedules, click the button that appears, then click Create Schedule.
  6. Set the time and day to run this job.
  7. Click Apply, then click OK.